2022 Street Enhancements

street enhancement
Street Enhancement on 2nd Street NW

Project Description: Annual street enhancements are bituminous pavement mill and overlay and patching projects that occur on various City streets and parking lots.  These improvements are not bid out to contractors, but instead are completed by City Streets Department staff.  Streets and parking lots are chosen for these improvements based primarily on pavement condition (PCI and visual inspection). 

Project Status: Click on the link below to view a map of the completed street enhancements for 2022.  The milling of these locations took place July 14th.  Paving began the week of July 25th and was completed the week of August 8th. 

Map of Completed 2022 Street Enhancements/Patching Locations

Project Costs & Funding: $100,000 is budgeted annually for Street Enhancements.  These improvements are 100% funded through Streets Capital and are not assessed to adjacent properties.