2023 Annual Street Enhancements

Project Description: Annual Street Enhancements are bituminous pavement mill and overlay and patching projects that occur on various City streets and parking lots.  These improvements are not bid out to contractors, but instead are completed by City Streets Department staff.  Streets and parking lots are chosen for these improvements based primarily on pavement condition (PCI and visual inspection). 

Project Status: Click on the link below to view a map of the street enhancements/patching locations completed in 2023.  These improvements began the week of July 24th and were completed the week of September 4th. 

Completed 2023 Street Enhancements/Patching Locations

Project Costs & Funding: $100,000 is budgeted annually for street enhancements.  These improvements are 100% funded through Streets Capital and are not assessed to adjacent properties.