2023 Crack Seal & Seal Coat

Project Description: This annual program consists of the crack sealing and seal coating of various City streets and parking lots.  Typically, new asphalt pavement is crack sealed and seal coated two (2) years after construction in order to extend its life.  Additional streets and parking lots are also selected for these treatments based on pavement condition (PCI) and as budgeted funding allows. 

2023 Crack Seal & Seal Coat Project Map

Project Status: A total of three (3) bids were opened on April 13th with the lowest bid being from Allied Blacktop Co. in the amount of $101,307.07.  This project was awarded on April 18th.  Crack sealing was completed August 9-10th and seal coating was completed on August 17th.  Seal coating clean-up (sweeping up excess chip rock) occurred the week of August 21st.   

Project Costs & Funding: Project costs totaled $91,160.47 and were 100% funded by Streets Capital.  City staff completed project design and inspection.