2023 Sanitary & Storm Sewer Repairs

Project Description: This project involved the replacement of a sanitary sewer riser pipe and services on 2nd Ave NW approximately 200 feet west of 4th St NW and storm sewer improvements at the following locations:

  1. 3rd St NW & 9th Ave NW (installed a manhole and flapper valve to relieve back yard flooding east of 3rd St NW during high rainfall events)
  2. 6th St NE (repaired a failing 42” storm pipe outlet to the City Marsh)
  3. 17th Ave NE just west of 4th St NE (installed larger pipe and catch basins to reduce street flooding during high rainfall events)

Project Status: On August 15th, a total of five (5) bids were received for this project with the lowest bid being from Selly Excavating Inc. in the amount of $103,509.  Construction began the week of September 25th and the project was completed on October 23rd.

Project Costs & Funding: Construction costs on this project totaled $81,675.43.  The sanitary sewer repairs on 2nd Ave NW totaled $24,667.43 and were funded through available 2023 sanitary sewer utility capital improvement funds.  The storm sewer improvements on 3rd St NW, 6th St NE, and 17th Ave NE totaled $57,008.00 and were funded with budgeted 2023 storm sewer utility capital improvement funds.  City staff completed project design and inspection.